NOTE: It is expected that this problem will be completed using an Excel spreadsheet using formulas. Please see the Excel Tutorial that is available under the course home tab.

The new president of the Wernecke Company was stumped. Why had profits gone down? He had directed the sales department to push the product with the highest contribution margin, and the sales department had come through with flying colors. The percent of flams sold had increased from 25% of units sold to 37.5% of units sold. So what happened?

Flims Flams
Sales Price per Unit $150 $500
Direct Materials per Unit $75 $200
Direct Labor Cost per Hour $25 $25
Direct Labor Hours per Unit 1 hour per unit 5 hours per unit
Number of Units Produced 25,000 15,000

The variable overhead for the coming year is estimated to be $3,000,000.

Required:
1. Calculate the Wernecke Company's estimated direct labor hours to produce flims and flams.

2. Calculate the predetermined variable overhead rate that will be used in the coming year using a traditional costing system based upon direct labor hours.

3. Using a traditional costing system based upon direct labor hours, compute the unit product costs for flims and flams as well as contribution margin per unit.

4. It has been suggested to the president to consider the use of an ABC costing system to allocate manufacturing overhead. Engineering studies have revealed the following information about estimated manufacturing activities for the coming year.
Activity Cost Pool Estimated Overhead Cost Expected Activity Level
Setups $850,000 200 setups
Scrap $350,000 500 units
Testing $200,000 5,000 tests
Machine related $1,600,000 100,000 Mhrs
Total $3,000,000
Calculate the separate predetermined overhead rates for each of the activities listed above.

5. The following data is available about the activity levels needed to produce the projected 25,000 units of Flims:

Activity Cost Pool Estimated Activity Level for Flims
Setups 50 setups
Scrap 200 units
Testing 2,000 tests
Machine related 12,500 Mhrs.
Calculate the expected variable overhead to be applied to Flims.

6. The following data is available about the activity levels needed to produce the projected 15,000 units of Flams:

Activity Cost Pool Estimated Activity Level for Gadgets
Setups 150 setups
Scrap 300 units
Testing 3,000 tests
Machine related 87,500 Mhrs.
Calculate the expected variable overhead to be applied to Flams.

7. Calculate the total overhead (total for company) that is expected to be applied to Flims and Flams.

8. Calculate the projected unit costs and unit contribution margins for Flims and Flams using ABC costing.

9. What conclusions can you drawn about the use of traditional costing vs. ABC costing for the Wernecke Company? What recommendations do you have for the president?

Purchase this Solution

Solution Summary

The solution is very easy to understand and concise. It is an excellent response for students who want to understand the concepts and then use the same concepts to solve similar problems in the future. Overall, an excellent response. The solution provides the necessary steps which are easy to follow.

Purchase this Solution


Free BrainMass Quizzes
Pricing Strategies

Discussion about various pricing techniques of profit-seeking firms.

Basics of Economics

Quiz will help you to review some basics of microeconomics and macroeconomics which are often not understood.

Elementary Microeconomics

This quiz reviews the basic concept of supply and demand analysis.

Economic Issues and Concepts

This quiz provides a review of the basic microeconomic concepts. Students can test their understanding of major economic issues.

Economics, Basic Concepts, Demand-Supply-Equilibrium

The quiz tests the basic concepts of demand, supply, and equilibrium in a free market.