P10-14 Vitalite, Inc. Comprehensive Variance Analysis

Not what you're looking for?

Ask Custom Question

Vitalite, Inc., produces a number of products, including a body- wrap kit. Standard variable costs relating to a single kit are given below:

Standard Quantity Standard Price Standard
or Hours or Rate Cost
Direct materials . . . . . . . . . . . . . . . . . . . . . . . . . . . ? $ 6 per yard $ ?
Direct labor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ? ? ?
Variable manufacturing overhead . . . . . . . . . . . . ? $ 2 per direct ?
labor- hour
Total standard cost per kit . . . . . . . . . . . . . . . . . . $ 42

During August, 500 kits were manufactured and sold. Selected information relating to the month's production is given below:

Variable
Materials Direct Manufacturing
Used Labor Overhead

Total standard cost* . . . . . . . . . . . . . . . . . . ? $ 8,000 $ 1,600
Actual costs incurred . . . . . . . . . . . . . . . . . $ 10,000 ? $ 1,620
Materials price variance . . . . . . . . . . . . . . . ?
Materials quantity variance . . . . . . . . . . . . . $ 600 U
Labor rate variance . . . . . . . . . . . . . . . . . . . ?
Labor efficiency variance . . . . . . . . . . . . . . ?
Variable overhead rate variance . . . . . . . . . ?
Variable overhead efficiency variance . . . . . ?
-----------------------
*For the month's production.

The following additional information is available for August's production of kits:

Actual direct labor- hours . . . . . . . . . . . . . . . . . . . .900
Difference between standard and actual cost per kit produced during August . . . . . . . . . . . . . . . . . . . . $ 0.14 U

Required:
1. What was the total standard cost of the materials used during August?
2. How many yards of material are required at standard per kit?
3. What was the materials price variance for August if there were no beginning or ending inventories of materials?
4. What is the standard direct labor rate per hour?
5. What was the labor rate variance for August? The labor efficiency variance?
6. What was the variable overhead rate variance for August? The variable overhead efficiency variance?
7. Complete the standard cost card for one kit shown at the beginning of the problem.

Purchase this Solution

Solution Summary

Your tutorial is attached with all the flags indicating "correct." I have included a "chart" to show how I solved for all this and then inserted my findings into the spreadsheet. This is fairly advanced and so is not suitable for a beginning without a basic understanding of variances.

Solution provided by:
Education
  • BSc, University of Virginia
  • MSc, University of Virginia
  • PhD, Georgia State University
Recent Feedback
  • "hey just wanted to know if you used 0% for the risk free rate and if you didn't if you could adjust it please and thank you "
  • "Thank, this is more clear to me now."
  • "Awesome job! "
  • "ty"
  • "Great Analysis, thank you so much"
Purchase this Solution


Free BrainMass Quizzes
Lean your Process

This quiz will help you understand the basic concepts of Lean.

Basic Social Media Concepts

The quiz will test your knowledge on basic social media concepts.

Organizational Behavior (OB)

The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.