Accounting : Performance Reports and Flexible Budget Approach

Not what you're looking for?

Ask Custom Question

The St. Lucia Blood Bank, a private charity partly supported by government grants, is located on the Caribbean island of St. Lucia. The Blood Bank has just finished its operations for September, which was a particularly busy month due to a powerful hurricane that hit neighboring islands causing many injuries. The hurricane largely bypassed St. Lucia, but residents of St. Lucia willingly donated their blood to help people on other islands. As a consequence, the Blood Bank collected and processed over 20% more blood than had been originally planned for the month.
A report prepared by a government official comparing actual costs to budgeted costs for the Blood Bank appears below. (The currency on St. Lucia is the East Caribbean dollar.) Continued support from the government depends on the Blood Bank's ability to demonstrate control over their costs.

St. Lucia Blood Bank
Cost Control Report
For the Month Ended September 30

Actual Budget Variance
Liters of blood collected 620 500 120

Variable costs:
Medical supplies $9,350 $ 7,500 $1,850 U
Lab tests 6,180 6,000 180 U
Refreshments for donors 1,340 1,000 340 U
Administrative supplies 400 250 150 U
Total variable cost 17,270 14,750 2,520 U
Fixed costs:
Staff salaries 10,000 10,000 0
Equipment depreciation 2,800 2,500 300 U
Rent 1,000 1,000 0
Utilities 570 500 70 U
Total fixed cost 14,370 14,000 370 U
Total cost $31,640 $28,750 $2,890 U

The managing director of the Blood Bank was very unhappy with this report, claiming that his costs were higher than expected due to the emergency on the neighboring islands. He also pointed out that the additional costs had been fully covered by payments from grateful recipients on the other islands. The government official who prepared the report countered that all of the figures had been submitted by the Blood Bank to the government; he was just pointing out that actual costs were a lot higher than promised in the budget.

Required:

1. Prepare a new performance report for September using the flexible budget approach. (Note: Even though some of these costs might be classified as direct costs rather than as overhead, the flexible budget approach can still be used to prepare a flexible budget performance report.)
2. Do you think any of the variances in the report you prepared should be investigated? Why?

Purchase this Solution

Purchase this Solution


Free BrainMass Quizzes
Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.

Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.

Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.