(Expected return and risk) Procter & Gamble is considering three possible capital investment
projects. The projected returns depend on the future state of the economy as given
here.
a. Calculate each project's expected return, variance, and standard deviation.
b. Rank the projects on the basis of (1) expected return and (2) risk. Which project would
you choose?
PROJECTED RETURN
State of the Probability of
Economy Occurrence 1 2 3
Recession 0.1 9% 3% 15%
Stable 0.7 13 10 11
Boom 0.2 17 22 5

Purchase this Solution

Solution Summary

This solution shows step-by-step calculations to determine the project's expected return, variance, and standard deviation. In addition, it ranks the projects on the basis of expected return and risk.

Purchase this Solution


Free BrainMass Quizzes
Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.

Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.

Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.