This content was STOLEN from BrainMass.com - View the original, and get the solution, here!

A production lot of 25 units required 103.6 hours of effort. Accounting records show that the first unit took 7 hours. What was the learning rate?

© BrainMass Inc. brainmass.com September 23, 2018, 11:36 pm ad1c9bdddf - https://brainmass.com/economics/production/learning-rate-165718

Solution Preview

A production lot of 25 units required 103.6 hours of effort. Accounting records show that the first unit took 7 hours. What was the learning ...

Solution Summary

The solution calculates the Learning rate.

$2.19