    A production lot of 25 units required 103.6 hours of effort. Accounting records show that the first unit took 7 hours. What was the learning rate?

    © BrainMass Inc. brainmass.com October 9, 2019, 8:53 pm ad1c9bdddf
    https://brainmass.com/economics/production/learning-rate-165718

    Solution Preview

    A production lot of 25 units required 103.6 hours of effort. Accounting records show that the first unit took 7 hours. What was the learning ...

    Solution Summary

    The solution calculates the Learning rate.