Learning rate; total cost of building
Not what you're looking for?
Company X collected the following cost data on the first 6 units of a new machine.
Unit number Cost, $ millions
1 300
2 244
3 211
4 194
5 179
6 169
Using Excel:
(a) Estimate the learning rate.
(b) Company X is bidding on a contract for 24 new machines. Explain how the estimated learning curve is helpful to Lockheed.
(c) Estimate the total cost of building 24 additional machines.
(d) Estimate the cost of building the 30th machine.
I have started this problem, but I am a little lost. Please help. Thanks!!
Purchase this Solution
Solution Summary
This post shows how to calculate learning rate, total cost of building in different number of machines
Solution Preview
See the attached file. Thanks
Company X collected the following cost data on the first 6 units of a new machine.
Unit number Cost, $ millions
x Yx Ln(x) Ln(Yx)
1 300 0.000 5.704
2 244 0.693 5.497
3 211 1.099 5.352
4 194 1.386 5.268
5 179 1.609 5.187
6 169 1.792 5.130
Using Excel:
(a) Estimate the learning rate.
The normal form of learning equation is Yx = Kx^n
Where:
x= unit number
Yx=Cost of producing the xth unit
K=Cost to procude the first unit
n=log b/log 2 where b is learning ...
Purchase this Solution
Free BrainMass Quizzes
Social Media: Pinterest
This quiz introduces basic concepts of Pinterest social media
Accounting: Statement of Cash flows
This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.
Understanding Management
This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.
SWOT
This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.
MS Word 2010-Tricky Features
These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.