    A portable generator is needed at a remote construction site. Two alternatives are being considered. Their annual fixed costs and operating and maintenance costs per hour are shown in the table below. The contractor runs three 8-hour shifts per day for 250 working days per year

    Generator 1

    Fixed cost per year $4000
    O&M Costs ($/hour) $7.00

    Generator 2

    Fixed Cost per year $8000
    O&M Costs $5.50

    a. How many hours per shift is a generator needed if the contractor is indifferent between the two generators?

    b. If the site requires a generator for 2.5 hours per shift, which generator is preferred, and what is its estimated annual cost?

    c. If the site requires a generator for 5.5 hours per shift, which generator is preferred, and what is its estimated annual cost?

    © BrainMass Inc. brainmass.com October 10, 2019, 3:23 am ad1c9bdddf
    https://brainmass.com/economics/finance/cost-analysis-417904

    Solution Preview

    Please refer attached file for better clarity of formulas.

    a.  How many hours per shift is a generator needed if the contractor is indifferent between the two generators?

    Let x be the number of hours per shift be x.
    Total cost in case of generator 1=4000+3*x*250*7=4000+5250x
    Total cost in ...