Operation management: Reducing project time

Not what you're looking for?

Ask Custom Question

Consider this network and the time and cost data shown below. The least costly way (assuming a linear time cost relationship) to reduce project time by one day is to reduce time be one day for activity:

Normal Crash
Activity Time Cost Time Cost
1-2 6 100 5 200
1-4 15 200 12 600
2-3 5 100 4 190
3-4 5 150 3 370
5-3 6 80 5 185
5-4 8 300 7 360

a) 1-2
b) 1-4
c) 2-3
d) Any of the above

I believe the answer is either B or D not sure.

Purchase this Solution

Solution Summary

This solution discusses reducing project time.

Solution Preview

Normal Crash Cost of reduction
Activity Time Cost Time Cost per day
1-2 6 100 5 200 =(200-100)/(6-5)=100
1-4 15 200 ...

Purchase this Solution


Free BrainMass Quizzes
Organizational Behavior (OB)

The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Income Streams

In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.