Estimating the manufacturing time

Not what you're looking for?

Ask Custom Question

It took a contractor 5000 hours to manufacture their first unit of an item. If the contractor expects to achieve a 94% unit learning curve, how many hours would be required to manufacture units 75-100? (Use the tables provided in the lesson).

A) 87,245

B) 682,979

C) 710,683

D) 83,844

Purchase this Solution

Solution Summary

Solution describes the steps to calculate the time needed to manufacture the product in the given range.

Solution provided by:
Education
  • BEng (Hons) , Birla Institute of Technology and Science, India
  • MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
  • "Thank you"
  • "Really great step by step solution"
  • "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
  • "Thanks Again! This is totally a great service!"
  • "Thank you so much for your help!"
Purchase this Solution


Free BrainMass Quizzes
Learning Lean

This quiz will help you understand the basic concepts of Lean.

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking

Income Streams

In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.

Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.