Construct a net material requirements plan
Not what you're looking for?
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Using this information, construct a net material requirements plan using the following on-hand inventory
Item On-hand inventory
S 20
T 20
U 40
V 30
W 30
X 25
Y 240
Z 40
Purchase this Solution
Solution Summary
Shows how to construct a net material requirements plan using the on-hand inventory
Solution Preview
Find the solution in attched excel sheet.
-First draw the Bill of materials and understand the hierarchy of items
-Make material requirements plans ...
Purchase this Solution
Free BrainMass Quizzes
Situational Leadership
This quiz will help you better understand Situational Leadership and its theories.
Introduction to Finance
This quiz test introductory finance topics.
Operations Management
This quiz tests a student's knowledge about Operations Management
Motivation
This tests some key elements of major motivation theories.
Social Media: Pinterest
This quiz introduces basic concepts of Pinterest social media