This will be our group discussion, which is used for preparing exam , but not assignment.

Ray company produces two different metal component used in medical equipment (component X and Component Y ). The company has three processes: molding, grinding, and finishing. In molding , molds are created, and molten metal is poured into the shell. Grinding removes the gates that allowed the molten metal to flow into the mold's cavities. In finishing, rough edges caused by the grinders are removed by small, handheld pneumatic tools. In molding, the setup time is one hour. The other two processes have no setup time required. The demand for Component X is 300 units per day, and demand for Component Y is 500 units per day. The minutes required per unit for each product are as follows:

Minutes Required per unit of Product

Product Molding Grinding Finishing
Component X 5 10 15
Component Y 10 15 20

The company operates on eight-hour shift. The molding process employs 12 workers (who each work eight hours). Two hours of their time, However, are used for setup(assuming both products are produced). The grinding process has sufficient equipment and workers to provide 200 grinding hours per shift.

The Finishing Department is labor intensive and employs 35 workers, who each work eight hours per day. The only significant unit-level variable cost are materials and power. For component X. the variable cost per unit is $40, and for component Y, it is $50. Selling prices for X and Y are $90 and $110, respectively. Berry's policy is to use two setups per day: an initial setup to produce all that is scheduled for Component X and a second setup(changeover) to produce all that is scheduled for component Y. The amount scheduled does not necessarily correspond to each product's daily demand.

discussion required:

1. Calculate the time( in minutes) needed each day to meet the daily market demand for component X and Component Y. What is the major internal constraint facing Berry Company.

2. Describe how berry should exploit its major binding constraint. Specifically identify the product mix that will maximize daily throughput.

3. Assume that manufacturing engineering has found a way to reduce the molding setup time from one hour to 10 minutes. Explain how this affects the product mix and daily throughput.

Purchase this Solution

Solution provided by:
Education
  • BE, Bangalore University, India
  • MS, University of Wisconsin-Madison
Recent Feedback
  • "Your explanation to the answers were very helpful."
  • "What does 1 and 0 means in the repair column?"
  • "Went through all of the formulas, excellent work! This really helped me!"
  • "try others as well please"
  • "Thank you, this helped a lot. I was not sure how to plug in those numbers to a formula. This was a great help. Now I have to figure out how to explain cost of capital is used in net present value analysis, and how cost of capital is used in net present value analysis. This stuff gets confusing."
Purchase this Solution


Free BrainMass Quizzes
SWOT

This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.

IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)

Organizational Behavior (OB)

The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations