Purchase Solution

Assessing the project's performance

Not what you're looking for?

Ask Custom Question

Where's my manners, can someone please help with this Thanks. I need to understand the basics of these problems.

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.

Activity C is finished. It finished 2 weeks late. It cost $100,000. And it was planned to have cost $110,000.

Activity D is beginning its forth of a planned 6-week schedule. It has cost $200,000 so far. It was estimated to cost $450,000 when finished. It is approximately 55% complete.

Using this data, calculate the following.

1. What are the PV, EV, and AC for the project?
2. What are the SV, CV, SPI, and CPI for the project?
3. Assess the project performance to date? Do you get to have the celebration?

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $250,000 when complete. Its costs so far are $165,000. It is 50% complete. The activity has completed 7 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 65% complete. It was to cost $190,000 when finished. Its costs to date are $150,000.

Activity C is finished. It finished 2 weeks late. It cost $200,000. And it was planned to have cost $250,000.

Activity D is at the end of its forth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete.

Using this data, calculate the following.

1. Calculate the CV, SV, CPI, and SPI for each activity and the total project.

Purchase this Solution

Solution Summary

Solution depicts the steps to calculate PV, EV, AC, SV, CV, CPI and SPI in the given cases

Solution Preview

1. What are the PV, EV, and AC for the project?

PV=150000*(5/15)+100000*(2/4)+110000+450000*(4/6)=$510,000
EV=150000*35%+100000*45%+110000*100%+450000*55%=$455,000
AC=45000+50000+100000+200000=$395,000

2. What are the SV, CV, SPI, and CPI for the project?

CV=EV-AC=455000-395000=$60,000
SV=EV-PV=455000-510000=-55000
CPI=EV/AC=455000/395000=1.1519
SPI=EV/PV=455000/510000=0.89216

3. Assess the project performance to date? Do you get to have the celebration?

CPI of 1.15 indicates that for every dollar spent, $1.15 earned value ...

Solution provided by:
Education
  • BEng (Hons) , Birla Institute of Technology and Science, India
  • MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
  • "Thank you"
  • "Really great step by step solution"
  • "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
  • "Thanks Again! This is totally a great service!"
  • "Thank you so much for your help!"
Purchase this Solution


Free BrainMass Quizzes
Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.

Basics of corporate finance

These questions will test you on your knowledge of finance.