Explore BrainMass

Explore BrainMass

    Special Order Bid Calculations

    Not what you're looking for? Search our solutions OR ask your own Custom question.

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    The following applies to all questions listed:

    Manufacturing support costs for products is predetermined at a rate of $60 per direct labor hour. An outlet has a bid in on a special order toy product. Estimates for the order include: Direct materials $40,000; direct labor 500 direct labor hours at $20 per hour; and a markup of 20%

    1) Support cost estimates for this special order total - $10,000, $30,000, $36,000, or none of these

    2) Estimated total product costs for this special order total - $50,000, $80,000, $96,000, or none of these

    3) The bid price for this special order should be - $50,000, $60,000, $80,000, or none of these

    © BrainMass Inc. brainmass.com March 4, 2021, 6:12 pm ad1c9bdddf
    https://brainmass.com/business/management-accounting/special-order-bid-calculations-34261

    Solution Preview

    Part 1
    Support cost estimates = $60/direct labor hour * 500 direct labor hours = $30,000.
    Answer: $30,000.

    Part 2
    Total product costs = ...

    Solution Summary

    This solution provides cost and bid price calculations for a bid.

    $2.49