    Calculating the Total Cost Transferred

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Question: Buklin Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 1,200 units. The costs and percentage completion of these units in beginning inventory were:

    Cost Percent Complete
    Materials costs:.......$17,500.....70%
    Conversion costs:....$5,400......60%

    A total of 8,000 units were started and 7,000 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department during the month:
    Materials costs: $177,188
    Conversion costs: $103,372

    The ending inventory was 60% complete with respect to materials and 30% complete with respect to conversion costs.

    The total cost transferred from the first processing department to the next processing department during the month is closest to:

    - $264,950
    - $263,200
    - $259,950
    - $265,650

    © BrainMass Inc. brainmass.com October 9, 2019, 9:56 pm ad1c9bdddf
    https://brainmass.com/business/management-accounting/calculating-the-total-cost-transferred-202313

    Solution Summary

    This solution is comprised of a detailed explanation to answer what is the total cost transferred from the first processing department to the next processing department during the month. The solution is provided in an attached Word document.

    $2.19