Finished Goods Inventory for Juanita Corporation
Not what you're looking for?
29. Juanita Corporation uses a Job-Order cost system and applies overhead on the basis of direct labor cost. At the end of October, Juanita had one job still in process. The job cost sheet for this job contained the following information:
Direct Material $480
Direct Labor $150
Manufacturing Overhead $600
An additional $100 of labor was needed in November to complete this job. For this job, how much should Juanita have transferred to Finished Goods Inventory in November when it was completed?
A) $1,330.
B) $ 500.
C) $1,230.
D) $1,730.
Purchase this Solution
Solution Summary
The solution explains the amount of goods transferred to finished goods inventory with calculations.
Solution Preview
The total amount in work in process is 480+150+600=1,230. An additional $100 of labor is needed. The overhead is applied ...
Purchase this Solution
Free BrainMass Quizzes
Balance Sheet
The Fundamental Classified Balance Sheet. What to know to make it easy.
Managing the Older Worker
This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce
Writing Business Plans
This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.
Motivation
This tests some key elements of major motivation theories.
Six Sigma for Process Improvement
A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.