Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from two different suppliers. The parts are needed throughout the entire 52-week year. Tegdiws are used at a relatively constant rate and are ordered whenever the remaining quantity drops to the reorder level. Widgets are ordered from a supplier who stops by every three weeks. Data for both products are as follows:
ITEM TEGDIW WIDGET
Annual demand 10,000 5,000
Holding cost (% of item cost) 20% 20%
Setup or order cost $150.00 $25.00
Lead time 4 weeks 1 week
Safety stock 55 units 5 units
Item cost $10.00 $2.00
a. What is the reorder quantity and what is the reorder point?
b. What is the inventory control system for Widgets?
Purchase this Solution
Solution Summary
This solution provides a detailed, step by step explanation of the given problem.
Purchase this Solution
Free BrainMass Quizzes
Lean your Process
This quiz will help you understand the basic concepts of Lean.
IPOs
This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)
Learning Lean
This quiz will help you understand the basic concepts of Lean.
SWOT
This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.
Team Development Strategies
This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.