NPV - A $500 feasibility study will be conducted at t = 0.

Not what you're looking for?

Ask Custom Question

Consider the following project data:
(1) A $500 feasibility study will be conducted at t = 0.
(2) If the study indicates potential, the firm will spend $1,000 at t = 1 to build a prototype. The best estimate now is that there is an 80 percent chance that the study will indicate potential, and a 20 percent chance that it will not.
(3) If reaction to the prototype is good, the firm will spend $10,000 to build a production plant at t = 2. The best estimate now is that there is a 60 percent chance that the reaction to the prototype will be good, and a 40 percent chance that it will be poor.
(4) If the plant is built, there is a 50 percent chance of a t = 3 cash inflow of $16,000 and a 50 percent chance of a $13,000 cash inflow.

If the appropriate cost of capital is 10 percent, what is the project's expected NPV?

Purchase this Solution

Solution Summary

Consider the following project data:
(1) A $500 feasibility study will be conducted at t = 0.
(2) If the study indicates potential, the firm will spend $1,000 at t = 1 to build a prototype. The best estimate now is that there is an 80 percent chance that the study will indicate potential, and a 20 percent chance that it will not.
(3) If reaction to the prototype is good, the firm will spend $10,000 to build a production plant at t = 2. The best estimate now is that there is a 60 percent chance that the reaction to the prototype will be good, and a 40 percent chance that it will be poor.
(4) If the plant is built, there is a 50 percent chance of a t = 3 cash inflow of $16,000 and a 50 percent chance of a $13,000 cash inflow.

Solution provided by:
Education
  • BE, Bangalore University, India
  • MS, University of Wisconsin-Madison
Recent Feedback
  • "Your explanation to the answers were very helpful."
  • "What does 1 and 0 means in the repair column?"
  • "Went through all of the formulas, excellent work! This really helped me!"
  • "try others as well please"
  • "Thank you, this helped a lot. I was not sure how to plug in those numbers to a formula. This was a great help. Now I have to figure out how to explain cost of capital is used in net present value analysis, and how cost of capital is used in net present value analysis. This stuff gets confusing."
Purchase this Solution


Free BrainMass Quizzes
MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.

Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.

Organizational Leadership Quiz

This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.

Lean your Process

This quiz will help you understand the basic concepts of Lean.