Explore BrainMass

Explore BrainMass

    Finance - Risk, Expected Return, NPV

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    41. Which of the following is the best measure of the systematic risk in a portfolio?
    a. variance
    b. standard deviation
    c. covariance
    d. beta

    42. The expected return for the asset shown in the following table is 18.75 percent. If the return distribution for the asset is described as below, what is the standard deviation for the asset's returns?

    Return Probability
    0.10 0.25
    0.20 0.50
    0.25 0.25

    a. 0.002969
    b. 0.000613
    c. 0.015195
    d. 0.054486

    43. Which of the following statements is most correct?

    a. If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
    b. If a project's internal rate of return (IRR) exceeds the cost of capital, then the project's net present value (NPV) must be positive.
    c. The IRR calculation implicitly assumes that all cash flows are reinvested at a rate of return equal to the cost of capital.
    d. Statements a and c are correct.
    e. None of the statements above is correct.

    44. You are deciding among two mutually exclusive projects. The two projects have the following cash flows:
    Project A Project B
    Year Cash Flow Cash Flow
    0 -$50,000 -$30,000
    1 10,000 6,000
    2 15,000 12,000
    3 40,000 18,000
    4 20,000 12,000

    The company's weighted average cost of capital is 10 percent. What is the net present value (NPV) of the project with the highest internal rate of return (IRR)?
    a. $ 7,090
    b. $ 8,360
    c. $11,450
    d. $12,510
    e. $15,200

    © BrainMass Inc. brainmass.com June 4, 2020, 2:00 am ad1c9bdddf
    https://brainmass.com/business/capital-budgeting/finance-risk-expected-return-npv-432505

    Solution Summary

    The solution answers 4 multiple choice question related to risk, expected return, NPV.

    $2.19

    ADVERTISEMENT