    If standard deviation is 10 units per week, lead time is 2 weeks, demand is 50 per week, lot size is lot - for - lot, and desired service level is 97.72%, what is the statistical reorder point?

    a - 100.00
    b - 112.6
    c - 128.3
    d - 221.7