    On June 1, two jobs were in process at Top Notch Painters, Inc. Details of the jobs follow:
    Job No. Direct Material Direct Labor
    P-20 $174 $64
    P-43 32 84

    Material inventory (for example, paint and sandpaper) on June 1 totaled $920, and $116 in material was purchased during the month. Indirect material of $16 was withdrawn from material inventory. On June 1, finished-goods inventory consisted of two jobs: P-12, costing $392, and P-26, costing $158. Both jobs were transferred to Cost of Goods Sold during the month.

    Also during June, jobs P-20 and P-43 were completed. To complete job P-20 required an additional $68 in direct labor. The completion costs for job P-43 included $108 in direct material and $200 in direct labor. Job P-45 was started during the period but was not finished. A total of $314 of direct material was used (excluding the $16 indirect material) during the period, and total direct-labor costs during the month amounted to $408. Manufacturing overhead has been estimated at 150 percent of direct-labor costs, and this relationship has been the same for the past few years.

    Required
    Compute the costs of jobs P-20 and P-43 and the balances in the June 30 inventory accounts.
    Job costs are collected in the three types of inventory accounts: material, work-in-process, and finished goods inventory.Compute the balance in each of the three accounts for Jobs P-20 and P-43. Compute the 6/1 balance in each account, post June events, and calculate the 6/30 ending balances.

    © BrainMass Inc. brainmass.com June 3, 2020, 7:50 pm ad1c9bdddf
    https://brainmass.com/business/business-management/job-costs-in-a-service-company-113226

    Solution Preview

    Job Costs in a Service Company
    On June 1, two jobs were in process at Top Notch Painters, Inc. Details of the jobs follow:
    Job No. Direct Material Direct Labor
    P-20 $174 $64
    P-43 32 84

    Material inventory (for example, paint and sandpaper) on June 1 totaled $920, and $116 in material was purchased during the month. Indirect material of $16 was withdrawn from material inventory. On June 1, finished-goods inventory consisted of two jobs: P-12, costing $392, and P-26, costing $158. Both jobs were transferred to Cost of Goods Sold during the month.

    Also during June, jobs P-20 and P-43 were completed. To complete ...

    Solution Summary

    This solution is comprised of a detailed explanation to compute the costs of jobs P-20 and P-43 and the balances in the June 30 inventory accounts, compute the balance in each of the three accounts for Jobs P-20 and P-43, and compute the 6/1 balance in each account, post June events, and calculate the 6/30 ending balances. This solution is provided in an attached Word document.