    A production line that produces protein bars operates 7 days per week, with three 8-hour shifts per day. The line was designed to produce bars at a rate of 800 per hour. Last week the line produced 120,000 bars. What is the utilization of this production line?

    © BrainMass Inc. brainmass.com June 4, 2020, 4:30 am ad1c9bdddf
    https://brainmass.com/business/business-management/calculating-the-utilization-in-the-given-case-564164

    Solution Preview

    Design Capacity of output=Number of hours in a shift*Number of shifts in a ...

    Solution Summary

    Solution depicts the steps to calculate the utilization of production line in the given case.