Hoping to increase the chances of reaching a performance goal, the director of a research project has assigned three separate research teams the same task. The director estimates that the team probabilities are .9, .8, and .7 for successfully completing the task in the allotted time. Assuming that the teams work independently, what is the probability that the task will not be completed in time?

Purchase this Solution

Solution Summary

This solution shows how to calculate the probability of a task not being completed on time by three separate research teams.

Solution Preview

Probability of task not completed = probability of team 1 does not complete X probability of team 2 does not complete X probability of team 3 not complete (remember that ...

Purchase this Solution


Free BrainMass Quizzes
Business Ethics Awareness Strategy

This quiz is designed to assess your current ability for determining the characteristics of ethical behavior. It is essential that leaders, managers, and employees are able to distinguish between positive and negative ethical behavior. The quicker you assess a person's ethical tendency, the awareness empowers you to develop a strategy on how to interact with them.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.