Purchase Solution

Thompson Construction - Construction Accounting

Not what you're looking for?

Ask Custom Question

THOMPSON CONSTRUCTION
Thompson Construction has a contract to remodel two Government warehouses for use as modern office space. The $900,000 contract was on March 1, with completion scheduled for 240 days after contract award. For 150 days, work proceeded as expected. Thompson completed work on Warehouse 1 and began work on Warehouse 2.

In removing the existing cracked and damaged Warehouse 2 floor, Thompson personnel uncovered what appeared to be ancient pottery. Thompson's Program Manager notified you and you ordered the contractor to suspend work until the Government could determine the source and nature of the pottery. University specialists were called in and began a careful excavation of the immediate area. Hundreds of pieces of pottery were removed and sent to nationally recognized experts for analysis. After several weeks, the experts determined that the scrap pottery has no historic value. When the warehouse was built there was a pottery factory about five miles away, and scrap from the factory had been used for fill during the original warehouse construction.

Thirty days after work was suspended, you notified Thompson that work could continue. Because of the delay, completion is now scheduled for 270 days after contract award.

As a result of the delay, Thompson submitted a request for equitable adjustment that includes $21,500 for indirect costs. Thompson calculated that this contract was 50 percent of company billings in July. In August, billings under the contract dropped to zero because of the stop work order. Half of the estimated $43,000 fixed indirect cost for August is $21,500.

Thompson also submitted the following information related to the request for equitable adjustment:
? Billings to the delayed contract from March thru August: $ 580,000

? Billings to all contracts from March thru August: $2,145,000

? Fixed indirect cost incurred from March thru August: $ 258,000

? Projected total billings to the delayed contract (including direct $930,000 costs related to the delay):

? Projected billings to all contracts during the term of the delayed $3,100,000 contract (including the period of the 30-day delay):

? Projected fixed indirect cost for during the term of the delayed $391,500 contract (including the period of the 30-day delay):

1. Using the Eichleay Formula, develop a position on the proposed equitable adjustment.

2. What would your position be if Thompson replaced 30 percent of the work?

Purchase this Solution

Solution Summary

The solution using the Eichleay Formula, develop a position on the proposed equitable adjustment.

Purchase this Solution


Free BrainMass Quizzes
Writing Business Plans

This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.

Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.

Understanding Management

This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Introduction to Finance

This quiz test introductory finance topics.