During the last quarter, BOSE Corp. recorded the following average times per order received and processed:

Wait time to start production.... 9.0 days
Inspection time..... 0.8 days
Process time... 3.0 days
Move time... 0.2 days
Queue time... 6.0 days

a. Compute the throughput time.

Throughput time =

b. Compute the manufacturing cycle efficiency (MCE)

MCE =

c. What percentage of the production time is spent in non value added activities?

d. Compute the delivery cycle time.

Delivery cycle time =

Attachments
Purchase this Solution

Solution Summary

This solution is comprised of a detailed explanation to compute throughput time, manufacturing cycle efficiency, percentage of the production time is spent in non value added activities, and compute the delivery cycle time.

Solution Preview

During the last quarter, BOSE Corp. recorded the following average times per order received and processed:

Wait time to start production.... 9.0 days
Inspection time..... 0.8 days
Process ...

Purchase this Solution


Free BrainMass Quizzes
Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.

Learning Lean

This quiz will help you understand the basic concepts of Lean.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.