During the last quarter, BOSE Corp. recorded the following average times per order received and processed:
Wait time to start production.... 9.0 days
Inspection time..... 0.8 days
Process time... 3.0 days
Move time... 0.2 days
Queue time... 6.0 days
a. Compute the throughput time.
Throughput time =
b. Compute the manufacturing cycle efficiency (MCE)
MCE =
c. What percentage of the production time is spent in non value added activities?
d. Compute the delivery cycle time.
Delivery cycle time =
Purchase this Solution
Solution Summary
This solution is comprised of a detailed explanation to compute throughput time, manufacturing cycle efficiency, percentage of the production time is spent in non value added activities, and compute the delivery cycle time.
Solution Preview
During the last quarter, BOSE Corp. recorded the following average times per order received and processed:
Wait time to start production.... 9.0 days
Inspection time..... 0.8 days
Process ...
Purchase this Solution
Free BrainMass Quizzes
Managing the Older Worker
This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce
Employee Orientation
Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.
Learning Lean
This quiz will help you understand the basic concepts of Lean.
Social Media: Pinterest
This quiz introduces basic concepts of Pinterest social media
MS Word 2010-Tricky Features
These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.