    52. The Jones Company has the following cost schedule:

    Output Total Cost
    (Units) ($)

    0 3000
    50 3750
    100 4275
    150 4675
    200 5000
    250 5300
    300 5700
    350 6250
    400 7050
    450 8225

    Prepare (a) average total cost and (b) marginal cost schedules for the firm.