Project K costs $52,125, its expected net cash inflows are $12,000 per year for 8 years, and its WACC is 12%, What is the projects NPV?
CFt = expected net cash flow at time t = $12,000
r = the projects cost of capital or WACC
N = is its life
The cast outflow is $52,125
Purchase this Solution
Solution Summary
Project's NPV is calculated.
Solution Preview
Project K costs $52,125, its expected net cash inflows are $12,000 per year for 8 years, and its WACC is 12%, what is the project's NPV?
Solution:
Year ...
Education
- BEng (Hons) , Birla Institute of Technology and Science, India
- MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
- "Thank you"
- "Really great step by step solution"
- "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
- "Thanks Again! This is totally a great service!"
- "Thank you so much for your help!"
Purchase this Solution
Free BrainMass Quizzes
Pricing Strategies
Discussion about various pricing techniques of profit-seeking firms.
Elementary Microeconomics
This quiz reviews the basic concept of supply and demand analysis.
Basics of Economics
Quiz will help you to review some basics of microeconomics and macroeconomics which are often not understood.
Economic Issues and Concepts
This quiz provides a review of the basic microeconomic concepts. Students can test their understanding of major economic issues.
Economics, Basic Concepts, Demand-Supply-Equilibrium
The quiz tests the basic concepts of demand, supply, and equilibrium in a free market.