Maximum stripping ratio

This content was STOLEN from BrainMass.com - View the original, and get the solution, here!

The total cost of ore mining at an open pit is $ 2.60 per tonne and that for waste is $ 1.90 per tonne. If the value of the ore is $ 14.90 per tonne and the company requires a 20% profit margin, what is the maximum stripping ratio?

© BrainMass Inc. brainmass.com September 22, 2018, 9:28 am ad1c9bdddf - https://brainmass.com/economics/finance/maximum-stripping-ratio-352641

Solution Preview

As the company needs 20% profit, let us maximum cost that it can afford to spend more tonne.

X + ...

Solution Summary

The total cost of ore mining at an open pit is $ 2.60 per tonne and that for waste is $ 1.90 per tonne. If the value of the ore is $ 14.90 per tonne and the company requires a 20% profit margin, what is the maximum stripping ratio?

$2.19