    Maximum stripping ratio

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    The total cost of ore mining at an open pit is $ 2.60 per tonne and that for waste is $ 1.90 per tonne. If the value of the ore is $ 14.90 per tonne and the company requires a 20% profit margin, what is the maximum stripping ratio?

    © BrainMass Inc. brainmass.com October 10, 2019, 1:52 am ad1c9bdddf
    https://brainmass.com/economics/finance/maximum-stripping-ratio-352641

    Solution Preview

    As the company needs 20% profit, let us maximum cost that it can afford to spend more tonne.

    X + ...

    Solution Summary

    The total cost of ore mining at an open pit is $ 2.60 per tonne and that for waste is $ 1.90 per tonne. If the value of the ore is $ 14.90 per tonne and the company requires a 20% profit margin, what is the maximum stripping ratio?

    $2.19