If a company is evaluating two independent projects. The company uses a 13.8 percent discount rate for such projects. Cost and cash flows are shown in the table. What are the NPVs of the two projects?

Year Project 1 Project 2
0 ($8,425,375) ($11,368,000)
1 $3,225,997 $2,112,589
2 $1,775,882 $3,787,552
3 $1,375,112 $3,125,650
4 $1,176,558 $4,115,899
5 $1,212,645 $4,556,424
6 $1,582,156
7 $1,365,882

Purchase this Solution

Solution Summary

The solution calculates the NPVs of given projects.

Solution provided by:
Education
  • BEng (Hons) , Birla Institute of Technology and Science, India
  • MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
  • "Thank you"
  • "Really great step by step solution"
  • "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
  • "Thanks Again! This is totally a great service!"
  • "Thank you so much for your help!"
Purchase this Solution


Free BrainMass Quizzes
Pricing Strategies

Discussion about various pricing techniques of profit-seeking firms.

Basics of Economics

Quiz will help you to review some basics of microeconomics and macroeconomics which are often not understood.

Elementary Microeconomics

This quiz reviews the basic concept of supply and demand analysis.

Economic Issues and Concepts

This quiz provides a review of the basic microeconomic concepts. Students can test their understanding of major economic issues.

Economics, Basic Concepts, Demand-Supply-Equilibrium

The quiz tests the basic concepts of demand, supply, and equilibrium in a free market.