Look back to the cash flows for projects F and G in Section 5 (page 112; also below). The cost of capital was assumed to be 10%. Assume that the forecasted cash flows for projects of this type are overstated by 8% on average. That is, the forecast for each cash flow from each project should be reduced by 8%. But a lazy financial manager, unwilling to take the time to argue with the project's sponsors, instructs them to use a discount rate of 18%.
a. What are the projects' true NPVs?

b. What are the NPVs at the 18% discount rate?

c. Are there any circumstances in which the 18% discount rate would give the correct NPVs? (Hint: Could upward bias be more severe for more-distant cash flows?)

C0 C1 C2 C3 C$ C5
F -9,000 6,000 5,000 4,000 0 0
G -9,000 1,800 1,800 1,800 1,800 1,800

Answers:

A. Formula Calculation TIP: Use POWER function to calculate (1+r)^t
NPV-Project F T C

NPV-Project G T C

B.
NPV-Project F T C

NPV-Project G T C

C.
T

Attachments

Solution Preview

Dear Student

Please see the attachment. For question 4, the level of Sales has not been provided. ...

Solution Summary

The solution does a great job of answering the question. The solution is brief and concise and very easy to follow along. All the steps are clearly shown and Excel formulas are provided so that the student can answer similar questions in the future. It can be easily understood by anyone with a basic understanding of the topic. Overall, an excellent solution.