Explore BrainMass
Share

expected NPV, standard deviation, and coefficient of variation

This content was STOLEN from BrainMass.com - View the original, and get the already-completed solution here!

Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:

Economic Scenario Probability of Outcome NPV
Recession 0.05 ($70 million)
Below average 0.20 (25 million)
Average 0.50 12 million
Above Average 0.20 20 million
Boom 0.05 30 million

Calculate the project's expected NPV, standard deviation, and coefficient of variation.

© BrainMass Inc. brainmass.com October 24, 2018, 9:41 pm ad1c9bdddf
https://brainmass.com/economics/economic-indicators/expected-npv-standard-deviation-and-coefficient-of-variation-134346

Solution Preview

Please see the attached file.

Scenario analysis is a process of analyzing possible future events by considering alternative possible outcomes (scenarios). The analysis is designed to allow improved decision-making by allowing more complete consideration of outcomes and their implications.
If we were to assign probabilities to each one of these scenarios we could calculate the expected NPV. We would consider precisely what economic situations would ...

Solution Summary

This job calculates the problem's expected NPV, standard deviation, and coefficient of variation.

$2.19
See Also This Related BrainMass Solution

What is the project's expected NPV, its standard deviation, and its coefficient of variation?

Shao Industries is considering a proposed project for its capital budget. The company estimates that the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts that there is only a 50 percent chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis:

Economic Scenario Probability of Outcome NPV
Recession 0.05 ($70 million)
Below average 0.20 (25 million)
Average 0.50 12 million
Above average 0.20 20 million
Boom 0.05 30 million

What is the project's expected NPV, its standard deviation, and its coefficient of variation?

View Full Posting Details