Explore BrainMass

Explore BrainMass

    expected NPV, standard deviation, and coefficient of variation

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:

    Economic Scenario Probability of Outcome NPV
    Recession 0.05 ($70 million)
    Below average 0.20 (25 million)
    Average 0.50 12 million
    Above Average 0.20 20 million
    Boom 0.05 30 million

    Calculate the project's expected NPV, standard deviation, and coefficient of variation.

    © BrainMass Inc. brainmass.com March 4, 2021, 7:57 pm ad1c9bdddf
    https://brainmass.com/economics/economic-indicators/expected-npv-standard-deviation-and-coefficient-of-variation-134346

    Solution Preview

    Please see the attached file.

    Scenario analysis is a process of analyzing possible future events by considering alternative possible outcomes (scenarios). The analysis is designed to allow improved decision-making by allowing more complete consideration of outcomes and their implications.
    If we were to assign probabilities to each one of these scenarios we could calculate the expected NPV. We would consider precisely what economic situations would ...

    Solution Summary

    This job calculates the problem's expected NPV, standard deviation, and coefficient of variation.

    $2.19

    ADVERTISEMENT