1) Key activity and tasks list for the following
a. Archive data from production based on thresholds to target archive repository
b. Retrieve data from archive repository and release for consumption
c. Purge data from a repository
Please use the following template
Srl No | Activity / Task | Milestone (Y/N) | Duration (in days, approx. is OK) | Predecessor (activity srl. No. this will help create dependency)

2) Recommendations on consolidating training, performance testing and other shared environments

© BrainMass Inc. brainmass.com March 22, 2019, 3:26 am ad1c9bdddf
https://brainmass.com/business/management-information-systems/data-archive-615890

Solution Preview

Attached

Archive data from production based on thresholds to target archive repository

Retrieve data from archive repository and release for consumption
S.No. Activity/Task Milestone (Y/N) Duration Predecessor
5. Create index Y 30 min Archive enable data (2)
6. Retrieve appropriate document using Doc_id and archive_id N 60 min Index has been created (5)

S.No. Activity/Task Milestone (Y/N) Duration Predecessor
1. Identify data to be ...

Solution Summary

Data archives are examined. The key activity and task lists for archive data, retrieve data and purge data is examined.