The Shawshank manufacturing co uses a job order cost system of accounting. The following info
was take from the books of the company after all posting had been completed at the end of January.

jobs completed direct materials cost direct labor cost factory overhead units completed
101 1800 2000 1000 200
102 1235 1250 890 150
104 900 850 350 100

a) Prepare journal entries to allocate cost of materials, labor and factory overhead to each job and transfer the cost of jobs completed to finished goods
b) Compute total production cost of each job
c) Computer the unit cost of each job
d) Computer the selling price per until for each job assuming a ark on percentage of 40%

Purchase this Solution

Solution Summary

The solution explains how to calculate the cost of the jobs.

Purchase this Solution


Free BrainMass Quizzes
Motivation

This tests some key elements of major motivation theories.

Transformational Leadership

This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.

MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.

Accounting: Statement of Cash flows

This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.