    The assignment problem constraint x41 + x42 + x43 + x44 <= 3 means:

    A) agent 4 can be assigned to three tasks.
    B) agent 3 can be assigned to four tasks.
    C) a mixture of agents 1, 2, 3, and 4 will be assigned to tasks 1, 2, or 3
    D) there is no feasible solution.

    © BrainMass Inc. brainmass.com June 3, 2020, 7:39 pm ad1c9bdddf
    https://brainmass.com/business/business-management/problem-constraint-107151

    Solution Preview

    In assignment problem decision variables are defined as
    Xij, where I is the agent or person or employee etc and j is task or job etc.

    Each decision variable is 1 if agent i is ...

    Solution Summary

    Solution contains answer of a multiple choice question (MCQ)