Westgate - percentage-of-completion method
Not what you're looking for?
In 2011, the Westgate Construction Company enter into a contract to construct a road for Santa Clara County for $10,000,000. The Road was completed in 2013. Information related to the contract is a follows:
2011 2012 2013
Cost incurred during year $2,400,000 $3,600,000 $2,200,000
Estimated Costs to complete as of year-end $5,600,000 $2,000,000 $ 0
Billings during the year $2,000,000 $4,000,000 $4,000,000
Cash collections during the year $1,800,000 $3,600,000 $4,600,000
Westgate uses the percentage-of-completion method of accounting for long term construction contracts.
1. Calculate the amount of gross profit to be recognized in each of the three years.
2. Prepare all necessary journal entries for each of the years (credit various accounts for construction costs incurred).
3. Prepare a partial balance sheet for 2011 and 2012 showing any items related to the contract.
4. Calculate the amount of gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
2011 2012 2013
Cost incurred during the year $2,400,000 $3,800,000 $3,200,000
Estimated costs to complete as of year- end 5,600,000 3,100,000 -0-
Complete the requirements of the Westgate Construction using the completed-contract method.
1. Calculate the amount of gross profit to be recognized in each of the three years.
2. Prepare all necessary journal entries for each of the years (credit various accounts for construction costs incurred).
3. Prepare a partial balance sheet for 2011 and 2012 showing any items related to the contract.
Purchase this Solution
Solution Summary
Your tutorial is attached. Click on the cells to see the computations. There are some notes about how to do the computations for gross profit and revenue recognized. This is a template for similar problems however loss contracts are handled differently so don't use these for contracts that have estimated contract-to-date losses.
Solution Preview
Your tutorial is attached. Click on the cells to see the computations. There are ...
Education
- BSc, University of Virginia
- MSc, University of Virginia
- PhD, Georgia State University
Recent Feedback
- "hey just wanted to know if you used 0% for the risk free rate and if you didn't if you could adjust it please and thank you "
- "Thank, this is more clear to me now."
- "Awesome job! "
- "ty"
- "Great Analysis, thank you so much"
Purchase this Solution
Free BrainMass Quizzes
Balance Sheet
The Fundamental Classified Balance Sheet. What to know to make it easy.
Organizational Leadership Quiz
This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.
Cost Concepts: Analyzing Costs in Managerial Accounting
This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.
Income Streams
In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.
Learning Lean
This quiz will help you understand the basic concepts of Lean.