    Standard cost system

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    The standard cost system unfavorable variances are also equivalent to under-applied over head as to favorable variances are equivalent to over-applied overhead.

    Thanks!

    © BrainMass Inc. brainmass.com June 3, 2020, 10:09 pm ad1c9bdddf
    https://brainmass.com/business/accounting/standard-cost-system-217734

    Solution Preview

    Hi,
    Please see the response to your posting as below:

    Under applied cost occurs when actual cost is greater than the allocated amount of overhead cost.
    Example:
    Let the standard overhead cost per unit be $2 per unit
    And ...

    Solution Summary

    Solution explains how the standard cost system unfavorable variances are also equivalent to under-applied over head as to favorable variances are equivalent to over-applied overhead.