S10-2

The following expenditures were incurred by Raven Run Industries. These expenditures relate to land, buildings and machinery and equipment.

Title Search $ 600
Architect's fees 3,000
Cash paid for land and old building 90,000
Removal of old building 16,000
Excavation before construction 18,000
Interest on short-term loans during construction 7,000
Machinery purchased 57,000
Freight on machinery purchased 1,200
Storage charges on machinery until construction was finished 1,900
New building construction 475,000
Assessment by city for drainage 1,500
Charges for transporting machinery from storage 700
Installation of machinery 2,100
Landscaping of facility 5,500

Provide a schedule showing the amount debited to Land, to Buildings, to Machinery and Equipment and to other expense accounts. The benefits of capitalizing interest during construction exceed the cost of implementation

Purchase this Solution

Solution Summary

Schedule amounts debited to land, building, machinery and equipment is examined.

Purchase this Solution


Free BrainMass Quizzes
Learning Lean

This quiz will help you understand the basic concepts of Lean.

Motivation

This tests some key elements of major motivation theories.

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking

Organizational Leadership Quiz

This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.

Understanding Management

This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.