3-13
Department
Milling Assembly
Direct labor-hours 8,000 75,000
Machine-hours 60,000 3,000
Manufacturing overhead cost $510,000 $800,000
Direct labor cost $72,000 $640,000

Required:
1. Compute the predetermined overhead rate to be used in each department.
2. Assume that the overhead rates you computed in (1) above are in effect. The job cost sheet for 407, which was started out and completed during the year, showed the following:

Department
Milling Assembly
Direct labor-hours 5 20
Machine-hours 90 4
Materials requisitioned $800 $370
Direct labor cost $45 $160

Compute the total overhead cost applied to Job 407.

3. Would you expect substantially different amounts of overhead cost to be charged to some jobs if the company used a plantwide overhead rate based on direct labor cost instead of using departmental rates? Explain. No computations are necessary.

Attachments
Purchase this Solution

Solution Summary

The answer contains computation of predetermined plant wide overhead rate on the basis of machine hours and direct albour hours and the application of overhead

Purchase this Solution


Free BrainMass Quizzes
Paradigms and Frameworks of Management Research

This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.

Accounting: Statement of Cash flows

This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.

Understanding Management

This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.