    Denver Manufacturing would like to do a better job budgeting for maintenance costs and, consequently, they have prepared a schedule showing maintenance costs and units produced for the past five months as follows:

    Number of units produced
    Total maintenance costs

    January -------------
    5,400
    $4,800

    February -----------
    6,600
    5,180

    March --------------
    4,900
    4,500

    April ----------------
    5,600
    4,900

    May -----------------
    6,000
    5,490

    Using the high/low method, what is the cost equation to predict total maintenance costs?

    Y = $2,540 - $.40x.

    Y = $2,540 + $.40x

    Y = $4,500 + $.40x

    Y = $4,500 - $.40x.

    © BrainMass Inc. brainmass.com June 3, 2020, 7:29 pm ad1c9bdddf
    https://brainmass.com/business/accounting/high-low-method-calculate-cost-function-100872

    Solution Preview

    In the high low method we use the highest and the lowest values