Compute the Prime Cost Variances for 2009

Not what you're looking for?

Ask Custom Question

During 2009, Toms Company produced a toy. The toy was assembled from material expected to cost $20 per ounce and two ounces were expected to be needed for each toy. Assembly was expected to require 1.5 hours per toy, at $10 per hour. During the year, variable factory overhead was applied at the rate of $4 per direct labor hour. 5,000 toys were produced during 2009, using 11,000 ounces of material costing $378,000, 8,000 hours of direct labor costing $90,000, and variable factory overhead totaling $28,000.

Compute the prime cost variances for 2009.

Purchase this Solution

Solution Summary

The solution computes the prime cost variances for 2009.

Solution Preview

Material price variance = (standard price - actual price)*actual quantity
=(20-34.36*)*11000 = ...

Purchase this Solution


Free BrainMass Quizzes
IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Motivation

This tests some key elements of major motivation theories.

Business Ethics Awareness Strategy

This quiz is designed to assess your current ability for determining the characteristics of ethical behavior. It is essential that leaders, managers, and employees are able to distinguish between positive and negative ethical behavior. The quicker you assess a person's ethical tendency, the awareness empowers you to develop a strategy on how to interact with them.