    Compute the Prime Cost Variances for 2009

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    During 2009, Toms Company produced a toy. The toy was assembled from material expected to cost $20 per ounce and two ounces were expected to be needed for each toy. Assembly was expected to require 1.5 hours per toy, at $10 per hour. During the year, variable factory overhead was applied at the rate of $4 per direct labor hour. 5,000 toys were produced during 2009, using 11,000 ounces of material costing $378,000, 8,000 hours of direct labor costing $90,000, and variable factory overhead totaling $28,000.

    Compute the prime cost variances for 2009.

    © BrainMass Inc. brainmass.com June 4, 2020, 1:45 am ad1c9bdddf
    https://brainmass.com/business/accounting/compute-prime-cost-variances-418270

    Solution Preview

    Material price variance = (standard price - actual price)*actual quantity
    =(20-34.36*)*11000 = ...

    Solution Summary

    The solution computes the prime cost variances for 2009.