    1. A grocery chain is considering the installation of a set of four self-checkout lanes. The new self-checkout lane setup will replace two old cashier lanes that were staffed by a cashier and bagger on each lane. They work 8-hour shifts. For the new self-checkout system, one cashier staffs all four self-checkouts (answering questions, checkng for unscanned items, taking coupons, etc.) Checkout in the new lanes takes 2 minutes (customers bag their own orders), while checkout in the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $.05 per checkout, while bagging (material) costs are $.10 per checkout with the old system and $.15 for the new system. The new lanes also require $100 in capital costs per shift. Assume that the lanes are always in use for 8 hours per day (one shift) and that a worker makes $10/hour.

    a) How many checkouts did the old system provide in a shift?

    b) How many checkouts does the new system provide

    c) Evaluate the system. (Compare the multifactor productivity of the systems and assess the new system in a short narrative)

    © BrainMass Inc. brainmass.com June 4, 2020, 2:28 am ad1c9bdddf
    https://brainmass.com/business/accounting/compare-multifactor-productivity-of-the-systems-459984

    Solution Preview

    1. A grocery chain is considering the installation of a set of four self-checkout lanes. The new self-checkout lane setup will replace two old cashier lanes that were staffed by a cashier and bagger on each lane. They work 8-hour shifts. For the new self-checkout system, one cashier staffs all four self-checkouts (answering questions, checkng for unscanned items, taking coupons, etc.) Checkout in the new lanes takes 2 minutes (customers bag their own orders), while checkout in the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $.05 per checkout, while bagging (material) costs are $.10 per checkout with the old system and $.15 for the new system. The new lanes also require $100 in capital costs per shift. Assume that the lanes are always in use for 8 hours per day (one shift) and that a worker makes $10/hour.

    a) How many checkouts did the old system provide in a shift
    Old System
    Two checkout lanes x 8 hours per shift = 16 hours x 60 =960 minutes
    Each Checkout takes 45 seconds = 45/60 = 0.75 minutes
    Number of checkouts per shift = 960/0.75 = 1,280 checkouts per ...

    Solution Summary

    1. A grocery chain is considering the installation of a set of four self-checkout lanes. The new self-checkout lane setup will replace two old cashier lanes that were staffed by a cashier and bagger on each lane. They work 8-hour shifts. For the new self-checkout system, one cashier staffs all four self-checkouts (answering questions, checkng for unscanned items, taking coupons, etc.) Checkout in the new lanes takes 2 minutes (customers bag their own orders), while checkout in the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $.05 per checkout, while bagging (material) costs are $.10 per checkout with the old system and $.15 for the new system. The new lanes also require $100 in capital costs per shift. Assume that the lanes are always in use for 8 hours per day (one shift) and that a worker makes $10/hour.

    a) How many checkouts did the old system provide in a shift?

    b) How many checkouts does the new system provide

    $2.19

    ADVERTISEMENT