Cadence and Cross master and departmental budgets

Not what you're looking for?

Ask Custom Question

Five years ago, Jack Cadence left his position at a large company to start Advanced Technologies Co. (ATC), a software design company. ATC's first product was a unique software package that seamlessly integrates networked PCs. Robust sales of this initial product permitted the company to begin development of other software products and to hire additional personnel. The staff at ATC quickly grew from three people working out of Cadence's basement to over 70 individuals working in leased spaces at an industrial park. Continued growth led Cadence to hire seasoned marketing, distribution, and production managers and an experienced accountant, Bill Cross.

Recently, Cadence decided that the company had become too large to run on an informal basis and that a formalized planning and control program centered around a budget was necessary. Cadence asked the accountant, Bill Cross, to work with him in developing the initial budget for ATC.

Cadence forecasted sales revenues based on his projections for both the market growth for the initial software and successful completion of new products. Cross used this data to construct the master budget for the company, which he then broke down into departmental budgets. Cadence and Cross met a number of times over a three-week period to hammer out the details of the budgets.

When Cadence and Cross were satisfied with their work, the various departmental budgets were distributed to the department manager with a cover letter explaining ATC's new budgeting system. The letter requested everyone's assistance in working together to achieve the budget objectives.

Several of the department managers were displeased with how the budgeting process was undertaken. In discussing the situation among themselves, they felt that some of the budget projections were overly optimistic and not realistically attainable.

Required:

How does the budgeting process Cadence and Cross used at ATC differ from recommended practice?

What are the behavioral implications of the way Cadence and Cross went about preparing the master budget?

Purchase this Solution

Solution Summary

The 315 word solution lists and explains four reasons why the existing budgeting process is not as effective as it could be. Each reason is demonstrated in a sentence or two.

Solution Preview

How does the budgeting process Cadence and Cross used at ATC differ from recommended practice?

1. Developing a budget is a process which should involve all the department managers because their input is invaluable for the information they possess. The managers certainly know and understand the direct costs in their departments.

2. In the beginning, the budget system is an educational tool to be used with managers. Even if the department managers have worked in other companies with budgets in ...

Purchase this Solution


Free BrainMass Quizzes
Motivation

This tests some key elements of major motivation theories.

Paradigms and Frameworks of Management Research

This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Understanding Management

This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.

Introduction to Finance

This quiz test introductory finance topics.