Explain why adding a personnel to a project that is behind schedule can make the project completion date even later?

Purchase this Solution

Solution Summary

This solution provides a discussion on how adding additional personnel to an existing project can either delay or help complete a project in time.

Solution Preview

It is a common notion that adding work force to a project in progress can help meet or beat project completion deadlines; however the opposite is true. The new addition to an existing team actually slows down work activities because in some shape or form every project team member must bring the new personnel up to speed on what s/he is doing or is to be done. It also depends on the new person's grasping power to come up to ...

Purchase this Solution


Free BrainMass Quizzes
Inserting and deleting in a linked list

This quiz tests your understanding of how to insert and delete elements in a linked list. Understanding of the use of linked lists, and the related performance aspects, is an important fundamental skill of computer science data structures.

Basic UNIX commands

Use this quiz to check your knowledge of a few common UNIX commands. The quiz covers some of the most essential UNIX commands and their basic usage. If you can pass this quiz then you are clearly on your way to becoming an effective UNIX command line user.

Java loops

This quiz checks your knowledge of for and while loops in Java. For and while loops are essential building blocks for all Java programs. Having a solid understanding of these constructs is critical for success in programming Java.

Excel Introductory Quiz

This quiz tests your knowledge of basics of MS-Excel.

Basic Networking Questions

This quiz consists of some basic networking questions.