Company A is considering a major expansion of its business. The details of the proposed expansion project are summarized below:
? The company will have to purchase $500,000 in equipment at t = 0. This is the depreciable cost.
? The project has an economic life of four years.
? The cost can be depreciated on a MACRS 3-year basis, which implies the following depreciation schedule:
MACRS
Depreciation

Year Rates
1 0.33
2 0.45
3 0.15
4 0.07

? At t = 0, the project requires that inventories increase by $50,000 and accounts payable increase by $10,000. The change in net operating working capital is expected to be fully recovered at t = 4.
? The project's salvage value at the end of four years is expected to be $0.
? The company forecasts that the project will generate $800,000 in sales the first two years (t = 1 and 2) and $500,000 in sales during the last two years (t = 3 and 4).
? Each year the project's operating costs excluding depreciation are expected to be 60% of sales revenue.
? The company's tax rate is 40%.
? The project's cost of capital is 10%.

What is the net present value (NPV) of the proposed project?

Purchase this Solution

Solution Summary

This solution is comprised of a detailed explanation and calculation to compute net present value (NPV) of the proposed project in an Excel file.

Solution Preview

Company A is considering a major expansion of its business. The details of the proposed expansion project are summarized below:
? The company will have to purchase $500,000 in equipment at t = 0. This is the depreciable cost.
? The project has an economic life of four years.
? The cost can be depreciated on a MACRS 3-year basis, which implies the following depreciation schedule:
MACRS
Depreciation

Year Rates
1 0.33
2 0.45
3 0.15
4 0.07

? At t = 0, the project requires that inventories increase by $50,000 and accounts payable increase by $10,000. The change in net operating working capital is expected to be fully recovered at t = 4.
? The project's salvage value at the end of four years is expected to be $0.
? The company forecasts that the project will generate $800,000 in sales the first two years (t ...

Purchase this Solution


Free BrainMass Quizzes
Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

Accounting: Statement of Cash flows

This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.

Basics of corporate finance

These questions will test you on your knowledge of finance.