A job, consisting of four elements, was randomly observed five times for a time study. The following table shows the results (figures are in seconds):

Work Elements Observations Performance Rating
1. Prepare patty 40 41 50 48 36 0.8
2. Cook first side 78 81 77 89 83 1.1
3. Flip, press, cook the other side 54 55 59 58 63 1.3
4. Assemble 28 24 27 26 32 0.9

A. What is the Normal Time (in seconds) for each work element?
B. What is the Standard Time (in seconds) for the job if there is a 20% of the job time allowance for personal needs and unavoidable work delays?

Purchase this Solution

Solution Summary

The following posting helps answer questions about normal time and standard time.

Solution Preview

A. Normal Time = Average(Observation) * Performance Rating
B. Standard Time = Normal Time * (1+0.2)

Work Observations ...

Purchase this Solution


Free BrainMass Quizzes
Marketing Research and Forecasting

The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.

Organizational Leadership Quiz

This quiz prepares a person to do well when it comes to studying organizational leadership in their studies.

Basic Social Media Concepts

The quiz will test your knowledge on basic social media concepts.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.