Consider the following data regarding factory overhead:
Variable Fixed
Budget for actual hours of input $45,000 $70,000
Applied 41,000 64,800
Budget for standard hours allowed
for actual output achieved ? ?
Actual incurred 48,500 68,500
Using the above data, fill in the following blanks with the variance amounts. Use F for favorable or U
for unfavorable for each variance.
Total Overhead Variable Fixed
1. Spending variance ______ ______ ______
2. Efficiency variance ______ ______ ______
3. Production-volume variance ______ ______ ______
4. Flexible-budget variance ______ ______ ______
5. Underapplied overhead ______ ______ ______

Purchase this Solution

Solution Summary

I put my work in Word so I could give you a "map" of how to layout the data without having to remember massive formulas.

Solution provided by:
Education
  • BSc, University of Virginia
  • MSc, University of Virginia
  • PhD, Georgia State University
Recent Feedback
  • "hey just wanted to know if you used 0% for the risk free rate and if you didn't if you could adjust it please and thank you "
  • "Thank, this is more clear to me now."
  • "Awesome job! "
  • "ty"
  • "Great Analysis, thank you so much"
Purchase this Solution


Free BrainMass Quizzes
Motivation

This tests some key elements of major motivation theories.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Operations Management

This quiz tests a student's knowledge about Operations Management

SWOT

This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.