1. A grocery chain is considering the installation of a set of four self-checkout lanes. The new self-checkout lane setup will replace two old cashier lanes that were staffed by a cashier and bagger on each lane. They work 8-hour shifts. For the new self-checkout system, one cashier staffs all four self-checkouts (answering questions, checkng for unscanned items, taking coupons, etc.) Checkout in the new lanes takes 2 minutes (customers bag their own orders), while checkout in the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $.05 per checkout, while bagging (material) costs are $.10 per checkout with the old system and $.15 for the new system. The new lanes also require $100 in capital costs per shift. Assume that the lanes are always in use for 8 hours per day (one shift) and that a worker makes $10/hour.

a) How many checkouts did the old system provide in a shift?

b) How many checkouts does the new system provide

c) Evaluate the system. (Compare the multifactor productivity of the systems and assess the new system in a short narrative)

Purchase this Solution

Solution Summary

1. A grocery chain is considering the installation of a set of four self-checkout lanes. The new self-checkout lane setup will replace two old cashier lanes that were staffed by a cashier and bagger on each lane. They work 8-hour shifts. For the new self-checkout system, one cashier staffs all four self-checkouts (answering questions, checkng for unscanned items, taking coupons, etc.) Checkout in the new lanes takes 2 minutes (customers bag their own orders), while checkout in the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $.05 per checkout, while bagging (material) costs are $.10 per checkout with the old system and $.15 for the new system. The new lanes also require $100 in capital costs per shift. Assume that the lanes are always in use for 8 hours per day (one shift) and that a worker makes $10/hour.

a) How many checkouts did the old system provide in a shift?

b) How many checkouts does the new system provide

Solution Preview

1. A grocery chain is considering the installation of a set of four self-checkout lanes. The new self-checkout lane setup will replace two old cashier lanes that were staffed by a cashier and bagger on each lane. They work 8-hour shifts. For the new self-checkout system, one cashier staffs all four self-checkouts (answering questions, checkng for unscanned items, taking coupons, etc.) Checkout in the new lanes takes 2 minutes (customers bag their own orders), while checkout in the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $.05 per checkout, while bagging (material) costs are $.10 per checkout with the old system and $.15 for the new system. The new lanes also require $100 in capital costs per shift. Assume that the lanes are always in use for 8 hours per day (one shift) and that a worker makes $10/hour.

a) How many checkouts did the old system provide in a shift
Old System
Two checkout lanes x 8 hours per shift = 16 hours x 60 =960 minutes
Each Checkout takes 45 seconds = 45/60 = 0.75 minutes
Number of checkouts per shift = 960/0.75 = 1,280 checkouts per ...

Purchase this Solution


Free BrainMass Quizzes
Learning Lean

This quiz will help you understand the basic concepts of Lean.

MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.