These three values should be first determined in order to know about the Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI) and Cost Performance Index (CPI) (Project Management).
These three values should be first determined in order to know about the Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI) and Cost Performance Index (CPI) (Project Management).
Value to cost (AC) is Cost Performance Index Cost Performance Index= 20,000/25,000= 0.8 The ratio of Earned Value to plan (PV) is Schedule Performance Index Schedule Performance Index= 20,000/23,000= 0.87 b.
Schedule performance index (SPI) begin{align} SPI = {EVover PV} end{align} SPI greater than 1 is good/favourable (ahead of schedule).
Project Status Report: The updated status report of the project by using earned value measurements is discussed below - Earned Value Management (EVM).
Index (SPI) The schedule efficiency ratio of earned value accomplished against planned value (SPI = EV/PV).
- Schedule performance index (SPI) = Earned value (EV) / Planned value (PV) Cost Performance Index/ Cost Efficiency (CPI): is the ratio of the sanctioned budget for work performed to what actually spent for the work.
107890 Earned Value Analysis-Spending variance, Schedule variance, Schedule Performance Index (SPI) , Cost Performance Index (CPI) Earned Value Analysis-Spending variance, Schedule variance, Schedule Performance Index (SPI) , Cost Performance Index (CPI
Use the schedule performance index (SPI) to estimate how long it will take to finish this project. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
CPI < 1.0 means that the task is over budget CPI = $100,000/$90,000 = 1.111 - UNDER BUDGET SPI (Schedule Performance Index) ? SPI=EV/PV ? schedule efficiency ratio of earned value accomplished against the planned value ?
SPI: Schedule Performance Index SPI=BCWP/BCWS = 1.0421 =$272,000 / $261,000 SPI<1 means project is behind schedule CPI: Cost Performance Index CPI= BCWP/ACWP 1.0074 =$272,000 / $270,000 CPI<1 means project