Metallurgical balance in mineral processing

Assume 2000 short tons of ore were mined, 200 tones were rejected as waste and the tonnage accepted for metallurgical treatment is 1800. Assay for the feed is 4%, for the concentrate is 4.4% and for the waste, 0.4%.