NPV and IRR Analysis

If I was considering the following projects which project should be accepted if the required rate of return for the projects is 10 percent? Compute NPVs and IRRs for both projects.

Year Project A Project B
0 (25000) (25000)
1 10000 0
2 9000 0
3 7000 0
4 6000 36000

Solution Preview

Please find my response in the attached file.

NPV and IRR analysis
--------------------------------------------------------------------------------
If I was considering the following projects which project should be accepted if the required rate of return for the projects is 10 percent? Compute NPVs and IRRs for both projects.

Year Project A Project B
0 (25000) (25000)
1 10000 0
2 9000 0
3 ...

Solution Summary

This solution is comprised of a detailed explanation and calculation to find NPV and IRR for Project A and B.