Finding the Critical Path and Project Duration

Not what you're looking for?

Ask Custom Question

The construction of a cottage requires the performance of certain tasks. The following table lists the various tasks with their priority relationship.

Activity o m p Predecessors
A 8 10 12 None
B 6 7 9 None
C 3 3 4 None
D 10 20 30 A
E 6 7 8 C
F 9 10 11 B,D,E
G 6 7 10 B,D,E
H 14 15 16 F
I 10 11 13 F
J 6 7 8 G,H
K 4 7 8 I,J
L 1 2 4 G,H

a. Calculate slack for each activity.
b. What is the critical path?
c. What is the project duration?
d. Determine the probability that the project will be finished in 80 days or less.

Purchase this Solution

Solution Summary

PERT is most commonly used technique in project management for determining project duration and critical path. Solution to given problem depicts the steps to determine the critical path, project duration and desired probability in the given case.

Solution Preview

Please refer to attached Excel spreadsheet for this full solution.

a. Calculate slack for each activity.

(Please refer attached file)

b. What is the critical path?
Activities with zero slack constitute the critical ...

Solution provided by:
Education
  • BEng (Hons) , Birla Institute of Technology and Science, India
  • MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
  • "Thank you"
  • "Really great step by step solution"
  • "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
  • "Thanks Again! This is totally a great service!"
  • "Thank you so much for your help!"
Purchase this Solution


Free BrainMass Quizzes
Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.

Introduction to Finance

This quiz test introductory finance topics.

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.

Marketing Research and Forecasting

The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.